Hi Experts ,
I've stumbled in a scenario that made me wonder.. What is the 'smart' way that the process update use when data got changed ?
In my case, I have a dimension that was processed well and then I've changed the query for that dimension at the DSV, so now it will return two different names (acting as attribute's name column) for the same code (acting as attribute's key column) .
Now I'm processing the dimension (process update) and it runs well ! When trying to process it with 'process data' option it fails !!
I know the 'process data' is rebuilding the attribute's data and hierarchy, So the failure is expected .
What about the process update ? is it looking only for key column changes ?
Any clarification will be much appreciated .
Regards, David .